Milestone M2 Exit Checklist

Date Deliverable Owner Status/Comment
10/15
  Send final COO Update request Team Leads Feedback being gathered.
  Generate License Updates Project Manager Final update dependent on approval of JOID OSSC request
10/22
Function freeze (midnight); All function delivered, unit tested and documentation updated. (no changes that break others, such as; project renames, API changes, API contract breaks All Complete
Send COO Update for Executive approval Release Manager Complete, COO Approved 10/26
10/23
Manual tests documented on the development web of the wiki Team Leads complete
  Code freeze (midnight), Only build breaking defects go into trunk, other fixes (such as code hygiene changes) not allowed All Complete, client programming model was checked on on 10/24 at 11:30AM
  verify available archive space Infrastructure Lead Complete
10/24
Branch M2 in SVN (6:00 AM Eastern) Build Lead Complete (2PM)
milestone build scripts Build Lead Complete
Assign Manual test to developers Lead Engineer complete
Begin Testing All complete Test Results
10/25
Test All Test Results
Document New Features for M2 Team Leads Complete
Create directories for M2 downloads on gpfs Build Lead Complete
Setup license click-through files in CLI download directories Infrastructure Lead Complete
10/26
Final build at Noon Build Lead Complete
Create Document web for milestone Infrastructure Lead complete, 10/30
Deliver Final build to projectzero.org. Infrastructure Lead (automated)
blog/forum/wiki/spotlight announcements Lead Engineer  
downloads counter script updates Infrastructure Lead Complete
10/29
Update wiki Download page to include M2 Brett complete 10/30
Update JavaDoc links to M2 Aaron complete 10/30
10/31
Confirm M2 bugs have been verified or moved to M3 Release Manager complete
Clean up M2 branches All  
Lessons Learned Release Manager  