M7 Exit Checklist

Completion of the M7 milestone will be staged. All runtime content will be complete by 5/9. All Application Builder content will be complete by 5/23. Documentation bugs can go into the build through 5/23.

Date Deliverable Owner Comment
5/5/08
  Solicit initial COO Update (features, contributors) Release Manager/Team Leads Complete
  Generate License Updates Project Manager Complete
Manual tests documented on the development web of the wiki Team Leads Complete
5/6/08
Runtime Function freeze (midnight); Only Approved MUST Fix bugs after this point (except doc) All Complete
  verify available archive space Infrastructure Lead Complete
5/7/08
Send COO Update for Executive approval Release Manager Complete
Branch M7 in SVN (6:00 AM Eastern) Michael Complete, 5/16 as sMash
milestone build scripts Build Lead Complete
Assign Manual test to developers Lead Engineer Complete
Begin Testing All Complete
5/8/08
Test All
Document milestone new feature highlights Team Leads Complete
Create directories for M7 downloads on gpfs Build Lead? Complete (sMash)
setup license click-through files in CLI download directories Infrastructure Lead Complete
5/9/08
Final build at Noon Build Lead Complete - work on M7/sMash will continue to 5/30
Create Document web for milestone Infrastructure Lead Complete
Deliver Final build to projectzero.org. Infrastructure Lead Complete - updates through 5/30
blog/forum/wiki/spotlight announcements Lead Engineer Complete
downloads counter script updates Infrastructure Lead Complete
5/12/08
Runtime Code freeze (midnight); Only Approved STOP SHIP bugs after this point (except doc) All Complete
Start 1 week Regression Test SVT Team Complete
Update wiki Download page to include M7 User Experience Lead Complete for sMash
Update JavaDoc links to milestone Build Lead Complete for sMash
Create next milestone wiki page Release Manager Hold for future planning
5/13/08
Confirm milestone bugs have been verified or moved to M3 Release Manager Complete
Clean up milestone branches All Complete
Lessons Learned Release Manager Complete
5/19/08
Start a second round of Regression Test SVT Team Complete
5/22/08
Last day for Documentation bugs All Complete