| Date | Deliverable | Owner | Comment |
| 07/16/08 |
| | Solicit initial COO Update (features, contributors) | Release Manager/Team Leads | Complete |
| | Generate License Updates | Project Manager | Complete |
| 07/21/08 |
| | Solicit final COO Update (features, contributors) | Release Manager/Team Leads | Complete |
| | Finalize License Updates | Project Manager | Complete |
| 07/28/08 |
| | Manual tests documented on the development web of the wiki | Team Leads | Complete |
| | Function freeze (midnight); All function delivered, unit tested and documentation updated. (no changes that break others, such as; project renames, API changes, API contract breaks | All | Complete |
| | Send COO Update for Executive approval | Release Manager | Complete |
| 07/29/08 |
| | Code freeze (midnight), Only build breaking defects go into trunk, other fixes (such as code hygiene changes) not allowed | All | Complete |
| | verify available archive space | Infrastructure Lead | Complete |
| | update license click-through to support the new milestone location | Infrastructure Lead | Complete |
| 07/30/08 |
| | Branch M1 in SVN (6:00 AM Eastern) | Build Lead | Complete |
| | milestone build scripts | Build Lead | Complete |
| | Assign Manual test to developers | Lead Engineer | Complete |
| | Begin Testing | All | Complete |
| 07/31/08 |
| | Test | All |
| | Document milestone new feature highlights | Team Leads | Complete |
| 08/01/08 |
| | Final build at Noon | Build Lead | Complete, 8/3 |
| | downloads counter script updates | Infrastructure Lead | Complete (no action required) |
| 08/04/08 |
| | Update wiki Download page to include Silverstone M1 | Infrastructure Lead | Complete |
| | Update Documentation page with pointers to Silverstone M1 Docs | Infrastructure Lead | Complete |
| | Update JavaDoc links to milestone | Build Lead | Complete |
| | blog/forum/wiki/spotlight announcements | Lead Engineer | Complete |
| | Create next milestone wiki page | Release Manager | Complete |
| 08/06/08 |
| | Confirm milestone bugs have been verified or moved to M2 | Release Manager | Complete |
| | Clean up milestone branches | All | Complete |
| | Lessons Learned | Release Manager | Defer to M2 |