Silverstone M4 Exit Checklist

Date Deliverable Owner Comment
11/19/08
  Solicit initial COO Update (features, contributors) Release Manager/Team Leads Complete
  Generate License Updates Project Manager NA
12/01/08
Manual tests documented on the development web of the wiki Team Leads Complete
Function freeze (midnight); All function delivered, unit tested and documentation updated. (no changes that break others, such as; project renames, API changes, API contract breaks All Complete
Send COO Update for Executive approval Release Manager Complete, 12/4
12/02/08
  Code freeze (midnight), Only build breaking defects go into trunk, other fixes (such as code hygiene changes) not allowed All Complete
  verify available archive space Infrastructure Lead Complete - 12/1
  update license click-through to support the new milestone location (/zero/sebring, /sMash/1.1.x) Infrastructure Lead complete - 12/2 (added sMash/1.1.x and sebring/M0, and discriminate between sebring/latest and silverstone/latest
12/03/08
Branch M4 in SVN (6:00 AM Eastern) Build Lead no M4 branch... this is release exit. There was a branch created for M0 Sebring
milestone build scripts Build Lead Complete for M0 Sebring, 12/10
Assign Manual test to developers Lead Engineer Complete
Begin Testing All Should occur on sMash/1.1.x (core) and sebring/latest (appbuilder); sMash/1.0.x and silverstone/latest from projectzero.org
Complete
12/04/08
Test All  
Document milestone new feature highlights Team Leads NA - only bug fixes
12/05/08
Final build at Noon Build Lead complete, 12/11
update website terminology - Sebring for latest, 1.1 for sMash Infrastructure Lead hold until 12/12
downloads counter script updates Infrastructure Lead (automatic for Silverstone, update possibly required for Sebring and sMash 1.1.x)
12/08/08
Update Download page to include Silverstone M4 Infrastructure Lead no silverstone M4 being created
Update Documentation page with pointers to Silverstone M4D Docs Infrastructure Lead no silverstone M4 being created
Update JavaDoc links to milestone Build Lead included within docs
blog/forum/wiki/spotlight announcements Lead Engineer Complete on 12/12
Create next milestone wiki page Release Manager Defer until Sebring plan in place
12/09/08
Confirm milestone bugs have been verified or moved to M3 Release Manager Complete, 12/12
Clean up milestone branches All Complete
Lessons Learned Release Manager Included as part of Iteration Zero for Sebring
12/12/08
blog/forum/wiki/spotlight announcements Lead Engineer Complete, 12/12
Update website download, doc pages and footer links
default download=sMash 1.1.x (home, download/index.php)
second-class download for sMash 1.0 (download/index.php - maybe a new sMash10.php page)
remove silverstone latest and milestone download links (download/latest.php)
add sebring latest download option (download/latest.php)
default getting started = sebring latest (home, footers, docs page)
default dev guide = sMash 1.1.x (home, footers, docs page)
Infrastructure Lead done - bug 7745
Update sitemap.xml with new docs locations Infrastructure Lead done
ADD TO FUTURE END-OF-MILESTONE CHECKLISTS
Delete Monaco milestone content (downloads and docs) Infrastructure lead done (archived)